Council proposal#107Final

The CR Secretariat Work Plan (Feb 2023 to July 2023)

Chain statusFinal

Final report approved. Released: 6 of 6.

Why this status?
Chain status
Final (read at block 2,344,800, 23 Nov 2026)
Payments
StageTypeAmountStatus on chainReleased
0Advance4611 ELAWithdrawnReleased
1Progress payment4611 ELAWithdrawnReleased
2Progress payment4611 ELAWithdrawnReleased
3Progress payment4611 ELAWithdrawnReleased
4Progress payment4611 ELAWithdrawnReleased
5Final payment4611 ELAWithdrawnReleased
Stage
Final
Approvals
12 approvals (8 needed)
Budget requested
27,666 ELA
Registered
Created
  1. Registered, done
  2. Council vote, done
  3. Public review, done
  4. Approved, done
  5. Final, done

Council vote closed: 12 approve, 12 seats. Approved; 8 approvals were needed.

This website is for reading. Voting, commenting, liking and following happen in the app. Vote, comment or follow in the app

Introduction

In the coming 6 months, the Secretariat would like to achieve the below goals as follows:

1, Transparent status update about the proposals: Track the progress of the proposals and approve their phased payment requests in a transparent way, which will be disclosed in CR Monthly
2, Regular update about the proposals to the Council: Regularly update on the status of the active proposals that are approved by CRC to the Council at a quarterly basis
3, Build the communication channel for Council members: Host Council Meetings on a biweekly basis (excluding national holidays)
4, Professional social media management
5, Six CR Monthly reports(EN) and six CR Monthly reports(CN) which will be released on CR website
6, Transparent financial update about CR Treasury: 1 CR Financial reports which will be released on CR website
7, Announcements/blogs with regards to CRC which will be released on CR website
8,Basic maintenence cost for Info site(no including labor cost)

Summary

This work plan proposal includes the same scope of work as the previous proposal titled "The Secretariat Work Plan from August 1st, 2022 to January 31st, 2023."

This proposal requests a six-month budget for the operation of the Secretariat from February 2023 to July 2023, with the budget size reduced to less than half under certain conditions.

Motivation

As a subsidiary body of the CR Council, the CR Secretariat’s main purpose is to support the operations of the CRC, which includes providing necessary support for the Council to reach CRC, and executing the CRC of the Council.

The CR Council has been established to reach a CR consensus. The CR Secretariat is the team responsible for executing the CR consensus. This work plan outlines the responsibilities of the CR Secretariat to ensure a healthy and transparent implementation of the CRC in the coming months.

Plan

The CR Secretariat would focus on the following tasks as listed below:

  1. Proposal follow-up

Proposal follow-up: It is the first and foremost task for the CR Secretariat to implement the proposal follow-up processes to maintain a healthy and thriving CRC mechanism. As for each proposal approved by CRC, the Secretariat shall review deliverables/related financial records and approve/reject staged payment requests to track the proper execution of the proposal.

I would strongly suggest all CR Council members pay more attention to completion payments and checkpoints when reviewing the proposals. Completion payments and checkpoints defined in the proposals enable the CR Secretariat to efficiently track progress of the proposals.

  1. Facilitate internal communication among the Council members and the communication between the Council and non-Council members

“Communication leads to community, that is, to understanding, intimacy and mutual valuing”. I am a true believer in the power of communication. As the Secretariat did last year, we will continue to facilitate both the internal communications within the Council and other communications between the Council members and Elastos community.

  1. CR social media management

Last year, the Secretariat reactivated the CR Twitter account. We plan to continue to manage Twitter in this workplan.

  1. CR monthly update (CN and EN)

To present the dynamics of the CRC and the proposals funded by the CR, the CR Secretariat will be responsible for publishing CR Monthly at the end of each month, which includes updates about CR Council motions and CR-funded proposals, or any other information that may be disclosed with the permission of CR Council. The CR Monthly Update delivers more transparency in terms of the execution of CRC.

  1. CR Financial update (CN and EN)

The CR Financial update will provide an update about how the funding in CR Treasure is allocated for approved proposals every 6 months.

  1. CR announcements/notifications/blogs with regards to the CRC and the Council

  2. Necessary involvement with some special proposals (eg, back up DPOS nodes, or CR Council, etc)

  3. Community questions relating to the Council and CRC

if you have any questions relating to the CRC and the Council, please reach out to the Secretariat at [email removed].

Budget

  • All unspent budget will be returned to CR at the end of the service time. The amount of ELA applied for in this proposal is calculated using 75% of the current ELA price (1ELA=$0.8). This method is to improve work efficiency and avoid a second budget proposal due to price fluctuations.

  • As per the previous work plan, the Secretariat would return the remaining ELA back to the CR Treasury at the begining of Feb of 2023.

  • The above budget is based on the following assumption: There are no more than 15 proposals funded by CR within the next 6 months. If this number is exceeded, the CR Secretariat will submit a second budget proposal.

Given the current market conditions, we decided to reduce the operating budget size for the Secretariat.
a) If the ELA price is below 1.0, the Secretariat General will work free of charge and all other team members will get about 50 percent of their orginal comp.The total budget will be between one-third to one-half of that for the previous work plan proposal
b) If the ELA price is between 1.0 and 1.5. The total budget will revert to the original budget in the previous work plan (Proposal 82).
c) If the ELA price is above 1.5. The total budget for the Secreatariat would be 35% higher than the budget in the previous work plan (Proposal 82).

Here is the budget when ELA price is below 1.0.

1), Social media management: 300 USDT per month
2), CR Monthly CN & EN (writer, editor, translator):estimated at 800 per month
3), CR Fiancial reports/CR announcements CN & EN (writer, editor, translator): estimated at 1000 USDT
4), Technical advisory/Necessary participation in some proposals: estimated at 500 USDT per month
5), Secretariat Management/Proposal tracking/other Secretariat operating matters: 0 USDT per month
6), Misc : 1000 USD in ELA per month, this will include the cost for Info site as showed in Proposal 103
Total estimate: 16600 USDT(27666 ELA)

Payments and milestones

Budget

StagePaymentPaid whenStatusAmount
0AdvanceComplete the tasks as defined in the proposalWithdrawn4,611 ELA
1Stage paymentComplete the tasks as defined in the proposalWithdrawn4,611 ELA
2Stage paymentComplete the tasks as defined in the proposalWithdrawn4,611 ELA
3Stage paymentComplete the tasks as defined in the proposalWithdrawn4,611 ELA
4Stage paymentComplete the tasks as defined in the proposalWithdrawn4,611 ELA
5Final paymentComplete the tasks as defined in the proposalWithdrawn4,611 ELA
Total27,666 ELA
  1. Advance · Stage 04,611 ELA

    Withdrawn

    Paid when Complete the tasks as defined in the proposal

  2. Stage payment · Stage 14,611 ELA

    Withdrawn

    Paid when Complete the tasks as defined in the proposal

  3. Stage payment · Stage 24,611 ELA

    Withdrawn

    Paid when Complete the tasks as defined in the proposal

  4. Stage payment · Stage 34,611 ELA

    Withdrawn

    Paid when Complete the tasks as defined in the proposal

  5. Stage payment · Stage 44,611 ELA

    Withdrawn

    Paid when Complete the tasks as defined in the proposal

  6. Final payment · Stage 54,611 ELA

    Withdrawn

    Paid when Complete the tasks as defined in the proposal

Total27,666 ELA

Milestones

  1. Milestone 1 · Stage 0

    Fulfill the tasks defined in the workplan

  2. Milestone 2 · Stage 1

    Fulfill the tasks defined in the workplan

  3. Milestone 3 · Stage 2

    Fulfill the tasks defined in the workplan

  4. Milestone 4 · Stage 3

    Fulfill the tasks defined in the workplan

  5. Milestone 5 · Stage 4

    Fulfill the tasks defined in the workplan

  6. Milestone 6 · Stage 5

    Fulfill the tasks defined in the workplan

Amounts

Budget amount
27666
Rejection amount
0
Rejection threshold
2248786.924877722

Proposal details

Proposal type
1

Updates

Withdrawal history

  1. Withdrawal 1
    Milestone key
    1
    Message
    Monthly payment
    Date
    Review reason
    Monthly payment
    Review opinion
    APPROVED
    Review date
  2. Withdrawal 2
    Milestone key
    2
    Message
    Monthly payment
    Date
    Review reason
    monthly payment
    Review opinion
    APPROVED
    Review date
  3. Withdrawal 3
    Milestone key
    3
    Message
    CR Secretariat Operating cost
    Date
    Review reason
    Monthly payment for CR Secretariat Operating cost
    Review opinion
    APPROVED
    Review date
  4. Withdrawal 4
    Milestone key
    4
    Message
    Monthly payment
    Date
    Review reason
    Monthly payment
    Review opinion
    APPROVED
    Review date
  5. Withdrawal 5
    Milestone key
    5
    Message
    Monthly Operating Cost
    Date
    Review reason
    Monthly Operating Cost
    Review opinion
    APPROVED
    Review date

Council opinions

In the order they voted

Council members vote in the app
  1. Phantz Club

    Approve

    Opinion not available

  2. infi

    Approve

    Opinion not available

  3. Jingyu Niu

    Approve

    Opinion not available

  4. DR

    Approve

    Opinion not available

  5. Elastos member

    Approve

    Opinion not available

  6. Rebecca Zhu

    Approve

    Opinion not available

  7. PG

    Approve

    Opinion not available

  8. Elation Studios

    Approve

    Opinion not available

  9. SJun Song

    Approve

    Opinion not available

  10. Elacity Official

    Approve

    Opinion not available

  11. MButcho • Nenchy

    Approve

    Opinion not available

  12. The Strawberry Council

    Approve

    Opinion not available

Vote text

  1. Vote 1
    Value
    support
    Reason
    Support Cassie and her team.
  2. Vote 2
    Value
    support
    Reason
    Support
  3. Vote 3
    Value
    support
    Reason
    Support
  4. Vote 4
    Value
    support
    Reason
    The Strawberry Council supports this proposal because it outlines a clear and comprehensive plan for the operation of the Secretariat from February 2023 to July 2023. The goals outlined in the proposal, such as transparent status updates about proposals, regular updates to the Council, and transparent financial updates about CR Treasury, align with the main purpose of the Secretariat, which is to support the operations of the CR Council. Additionally, the plan includes a focus on proposal follow-up, which is essential for maintaining a healthy and thriving CR Council mechanism.
  5. Vote 5
    Value
    support
    Reason
    Approved
  6. Vote 6
    Value
    support
    Reason
    Keep moving
  7. Vote 7
    Value
    support
    Reason
    Approved. The Secretariat team is important for the day to day running of the CRC.
  8. Vote 8
    Value
    support
    Reason
    support
  9. Vote 9
    Value
    support
    Reason
    Support, Cassie with the team does a great job and her working for free, if the ELA price is below 1 USD, sets a great example.
  10. Vote 10
    Value
    support
    Reason
    支持
  11. Vote 11
    Value
    support
    Reason
    The CR Secretariat plays a crucial role in supporting the operations of the CR Council, which includes providing necessary support for the Council to reach CR consensus and executing the CR consensus of the Council. The work plan proposal outlines the responsibilities of the Secretariat for the upcoming six-month period and lays out the tasks and goals that the Secretariat will focus on to ensure healthy and transparent implementation of the CR consensus.
  12. Vote 12
    Value
    support
    Reason
    Phantz NFT holders vote yes

Vote-history text

No vote-history text was listed.

No comments yet.